R-TOSS shows order status ONLY for Terra-manufactured items that have been released to production. If you see an error message, call to verify that your order has been released and that it contains Terra-made items
All products on your order carry a single TUI Ref Number
Before production, Terra schedules days for each task and establishes a Plan Schedule
During production, actual progress is scanned for each task
Daily, actual progress is used to issue a Projected Schedule
Daily, all data are uploaded to the R-TOSS and displayed below
Work Days for each product are shown as:
Green = Completed
Yellow = Open
Blue = Ahead of Schedule
Red = Behind Schedule
In the sample data below:
Item One: Product # 1681-48
RTOSS indicates the job was completed in 20 days, three days fewer than estimated (underrun days shown in blue)
Item Two: Product # 1681-78
RTOSS indicates the job was completed in two days, five days fewer than estimated (underrun days shown in blue)
Item Three: Product # 3305-00F-CL
RTOSS indicates the job was completed in 26 days, five days more than estimated (overrun days shown in red)